Project record
2.4 km of river embankment reinforced to protect 600 homes and 340 acres of farmland.
Muazzempur
45% complete
Erosion during the 2025 monsoon removed roughly 40 metres of embankment crest across three stretches, leaving Moazzempur ward 9 exposed to river flooding.
Repair work includes geo-bag revetment, crest raising and turfing, sequenced to complete before the next high-water season.
Recorded progress
18 APR18 Apr 2026
Water Development Board approved the revetment and crest-raising design.
5% complete
Recorded by Constituency office
22 JUL22 Jul 2026
Geo-bag revetment completed on the most exposed stretch before high water.
45% complete
Recorded by Constituency office
Photographs recorded at each stage as a visual evidence trail.
Condition before work
Erosion assessment and design
Report · PDF · 1 KB · 18 Apr 2026
Placeholder documents. Internal or sensitive documents are never published here.
Status, progress, budget and completion-date changes are logged.
Repair breached embankment stretches ahead of high water and maintain an annual pre-monsoon inspection record.
InfrastructureSherpur
1.1 km covered drain to stop bazaar flooding and connect 210 shops to a proper outfall.
InfrastructureSherpur
1.8 km of village road rebuilt with concrete surfacing, roadside drainage and two culverts.
EnvironmentMuazzempur
180 solar street lights across six unions, prioritising school routes and bazaar approaches.