Project record
1.1 km covered drain to stop bazaar flooding and connect 210 shops to a proper outfall.
Sherpur
22% complete
The bazaar sits in a natural low point. Waste water pooled around food stalls for most of the year, a repeated source of complaints from traders and the union health inspector.
The project builds a 1.1 km covered RCC drain with silt traps and a new outfall into the Narasunda canal.
Recorded progress
14 JUL14 Jul 2026
Alignment agreed with the bazaar committee to limit trading disruption.
10% complete
Recorded by Constituency office
11 AUG11 Aug 2026
Eastern stretch excavation underway with temporary vendor relocation.
22% complete
Recorded by Constituency office
Photographs recorded at each stage as a visual evidence trail.
Condition before work
Status, progress, budget and completion-date changes are logged.
Rebuild the roads that go under water each monsoon and give the bazaars a covered drainage network with a proper outfall.
InfrastructureSherpur
1.8 km of village road rebuilt with concrete surfacing, roadside drainage and two culverts.
InfrastructureMuazzempur
2.4 km of river embankment reinforced to protect 600 homes and 340 acres of farmland.
Social WelfareSherpur
Ward-level camps to enrol eligible residents missing from the social safety-net registers.