1.8 km of village road rebuilt with concrete surfacing, roadside drainage and two culverts.
Sherpur
100% complete
The Ward 7 connector road links Sherpur bazaar with four para settlements and the union health centre. Before the work, the earthen surface flooded for roughly four months each year, cutting off ambulance and school access.
The rebuilt road uses a 3.6 metre concrete carriageway with compacted shoulders, two box culverts and 900 metres of side drain to move monsoon water into the existing canal.
Recorded progress
12 MAR12 Mar 2026
Approval order issued by LGED with a four-month work schedule.
Recorded by Constituency office
20 MAR20 Mar 2026
Site cleared and sub-base excavation started from the bazaar end.
8% complete
Recorded by Constituency office
15 APR15 Apr 2026
Both box culverts cast and cured at the canal crossings.
35% complete
Recorded by Constituency office
20 MAY20 May 2026
1.2 km of the carriageway laid; drainage work running in parallel.
65% complete
Recorded by Constituency office
28 JUN28 Jun 2026
Full 1.8 km handed over twelve days ahead of schedule, including street lighting.
100% complete
Recorded by Constituency office
Photographs recorded at each stage as a visual evidence trail.
Condition before work
Completion certificate
Completion · PDF · 1 KB · 28 Jun 2026
Tender notice and bid summary
Tender · PDF · 1 KB · 20 Mar 2026
Project approval order
Approval · PDF · 1 KB · 12 Mar 2026
Placeholder documents. Internal or sensitive documents are never published here.
Status, progress, budget and completion-date changes are logged.
Rebuild the roads that go under water each monsoon and give the bazaars a covered drainage network with a proper outfall.
InfrastructureSherpur
1.1 km covered drain to stop bazaar flooding and connect 210 shops to a proper outfall.
InfrastructureMuazzempur
2.4 km of river embankment reinforced to protect 600 homes and 340 acres of farmland.
Social WelfareSherpur
Ward-level camps to enrol eligible residents missing from the social safety-net registers.